Building Consent & CCC8 Key StagesComplete Process
Building Consent & CCC
A simple step-by-step guide to take you from contract signing to receiving your Code Compliance Certificate.
Quick Answer
The process does not finish when council approves your building consent. You still need the approved documents, inspections, any variation approvals and the final CCC before the project is officially complete.
Building consent gives permission to build
Construction must follow the approved plans and inspection schedule
The Code Compliance Certificate confirms the finished work is accepted by council
Step 1
Contract & Project Start
- We both sign the contract
- You pay the first invoice (deposit)
- We start your project after the payment is received
Step 2
Property Information
- You send us your Property File, Record of Title, and Owner's Authorisation Letter
- If there are no existing plans or they are too old, we'll scan and measure your house in 3D to create accurate 2D and 3D drawings
Extra fee for 3D scanning
Step 3
Compliance & Building Consent
- We prepare the architectural drawings for your Building Consent (BC)
- You'll receive the BC drawings for your review and sign-off
- We prepare and complete the online building consent application
- You choose whether to pay the council fee directly, or send it to us to pay on your behalf
- Once paid, we'll send you the confirmation and BCO number
Step 4
Council Review Process
- The council takes up to 20 working days to review your application
- If they request more information (RFI), we'll respond for you — no extra fee
- When the council is satisfied, the BC is technically approved
- The council sends their final invoice for processing
- You pay us the final project invoice (due before release)
- Once both invoices (ours and council's) are paid, we'll send you a link to the approved Building Consent documents
You now have the approved plans and can start construction — not before
Step 5
Construction Stage
- Your builder must book inspections as listed in the approved documentation
- Each inspection must pass before moving to the next stage
- If an inspection fails, the builder must fix the issue and rebook
Step 6
Variations (Changes During Construction)
Minor Variations
- Small material or detail updates
- Can usually be approved on-site by the council inspector
- Might require updated drawings or supporting documents
Major Variations
- Removing or adding walls, or changing the footprint
- Need a new consent process, new drawings, and council fees
- Similar to a new Building Consent application
Step 7
Near Completion
- If you want to use part of the building before full completion, you can apply for a Certificate for Public Use (CPU)
- CPU requires its own council fee, drawings, and a short report
- Once all inspections are passed, the council will carry out a final inspection
Step 8
Code Compliance Certificate (CCC)
- After the final inspection passes, you (or your builder) apply for the CCC
- Pay the council fee for CCC processing
- Once approved, you receive the Code Compliance Certificate
- Your project is officially complete, and the council updates its records
Congratulations! Your building is now fully compliant and certified.