How to Respond to a Council RFI
A practical step-by-step guide to council Requests for Information during building consent: how RFIs happen, how they pause the process, how we coordinate responses, and how we keep applications moving.
Quick Answer
An RFI is council asking for clarification or missing information before a building consent can continue. The best response is complete, coordinated and easy for the processing officer to review.
Prevent RFIs Before Lodgement
The best way to handle a Request for Information is to reduce the chance of receiving one in the first place. This starts before lodgement, with a complete, organised and coordinated building consent package.
- We prepare a robust set of architectural plans and consent notes.
- We check that key construction details, compliance pathways and specifications are clear.
- We coordinate engineer, drainage, H1, fire, planning or specialist information where required.
- For complex projects, a pre-application meeting or early pathway advice may reduce uncertainty before lodgement.
No one can guarantee zero RFIs. Council can still ask questions depending on the project, reviewer, council requirements and risk profile.
Acknowledge the Paused Timeline
When council issues an RFI, the building consent process is no longer moving normally. The application waits while the requested information is prepared and sent back.
- The council processing clock can pause while the RFI is open.
- The application may sit in a queue until the response is received and reviewed.
- Delays can become longer if consultant responses or revised drawings are needed.
- We start working on RFIs as soon as possible because reducing delay is one of our main priorities.
Fast coordination matters because an incomplete or partial response can create another review cycle.
Read, Classify and Allocate Each RFI Item
Not every RFI item belongs to the architect. A proper response starts by separating the questions into the right responsibility groups.
- Architectural details, weathertightness notes or drawing coordination.
- Structural engineering, civil, drainage, stormwater or H1 energy efficiency.
- Fire, accessibility, commercial, planning, forms or administrative clarification.
- An item-by-item response list showing who must answer each issue and what is still pending.
Coordinate Consultants for Missing Details
Many RFIs ask for information that sits outside architectural scope. Structural engineering, drainage, stormwater, producer statements, calculations or specialist reports may need to be updated.
- We send the relevant RFI items to the correct specialist.
- The consultant may provide a response letter, revised drawings, calculations or supporting documents.
- Where suitable, we include the consultant response inside the main RFI response package.
- Where separate documents are needed, we submit them together with the architectural response so council receives one coordinated package.
Third-party consultant responses, specialist redesigns, new reports or changes outside the original scope may involve separate fees.
Prepare Revised Plans, Clouded Changes and a Response Letter
A good RFI response should make council review easier. It should not force the officer to search through unmarked drawings or guess which document answers each question.
- We prepare a response letter addressing each RFI item one by one.
- We revise drawings, details, notes or specifications where required.
- Changes are clouded or clearly marked, usually in red, with a revision number or revision letter.
- Consultant letters and revised documents are attached or referenced clearly.
- The response package is organised so council can track what has changed and why.
Submit a Comprehensive RFI Response
Once all information is gathered, we submit the complete RFI response package to council. The aim is to reduce back-and-forth and avoid another unnecessary RFI cycle.
- We check that every RFI item has been answered or allocated.
- We submit revised drawings, consultant documents and response letters together.
- We avoid partial responses where possible because they can extend delays.
- Once council receives the response, the application can move back into review and the processing clock can restart.
Council fees vary by council and current fee schedule. Specialist responses may also affect timing and cost.
Handle Further RFI Rounds if Council Needs More
Sometimes council accepts most of the response but asks for another clarification. This can happen because the project is complex, the first response reveals another issue, or the officer wants confirmation of a particular compliance pathway.
- We review any further RFI round quickly.
- We identify whether the issue is new, unresolved or simply a request for confirmation.
- We coordinate the required response again until council has the information it needs.
- We keep the client informed so the process feels managed rather than uncertain.
Move to Technical Approval and the Next Stage
Once council is satisfied that all required information has been provided, the building consent can continue toward technical approval.
- Council completes its review of the RFI response.
- If there are no further RFIs, the project can move toward approval.
- Council may issue its final invoice before releasing the approved documents.
- Once all required invoices are paid, the approved building consent documents are released.
- After approval, the project moves into the construction and inspection process.
The RFI stage is still part of consent processing. Construction should not begin until building consent has been granted.
Why Council RFIs Happen
RFIs are not always a sign that the project is wrong. Sometimes council wants confirmation, a clearer compliance pathway, a missing detail or a specific reference.
Different Types of RFIs
Some items are solved with a quick clarification. Others require revised drawings, calculations or consultant letters.
How RFIs Can Improve the Final Project
RFIs can be stressful, but they often help resolve construction issues before work starts.
Official References
MBIE Building Performance explains that a building consent application should be clear, correct, complete and include suitable detail.
Common Questions
What does RFI mean?
RFI means Request for Information. It is council asking for missing information, clarification, revised drawings or supporting documents before the building consent can continue.
Are RFI responses included?
For building consent applications prepared by ArchSolutioNZ, RFI response coordination and architectural responses are generally included within the agreed service scope. Consultant fees, major redesign or work outside the original scope may be separate.
Can you guarantee no RFIs?
No. We prepare robust documentation to reduce avoidable RFIs, but council can still ask questions depending on the project, reviewer, council requirements, specialist inputs and risk profile.
What happens after an RFI response is submitted?
Council reviews the response. If satisfied, the application continues toward approval. If more clarification is needed, council may issue another RFI round.
Can an RFI change the design?
Sometimes. An RFI may require better details, larger timber sizes, improved weathertightness, more evidence or changes to resolve a compliance issue. If the change is major, it may affect scope, cost or programme.