    Building Your Granny Flat Step by Step

    A plain-language walkthrough of the new building consent exemption for small standalone dwellings under the Building Act 2004, from January 2026.

    Quick Answer

    The granny flat exemption can remove the normal building consent pathway for some small standalone dwellings, but it does not remove the need for the right checks, design documents, licensed professionals, PIM process, records and completion evidence.

    19 steps across 6 phases
    PIM required before building work starts
    Council stores final documentation but does not issue a CCC under the exemption

    Who does what

    ArchSolutioNZ
    You
    Council
    Builder / Trades
    Both

    Phase 1 — Getting started

    Step 1
    You

    Contact ArchSolutioNZ

    Call, email, or fill out an enquiry form on our website. Tell us roughly what you have in mind — where the property is, what you want to build, and any timeline or budget ideas.

    • No commitment required at this stage
    • We'll let you know if the granny flat exemption is likely to apply to your situation
    • We can also flag if you might need a standard building consent instead
    Step 2
    ArchSolutioNZ

    Initial consultation & feasibility

    We'll review your site details and discuss whether your proposed granny flat qualifies for the consent exemption. The dwelling must meet all of these conditions:

    • New build only — not an addition or conversion of an existing structure
    • Single storey (no mezzanine)
    • Standalone — not attached to another building
    • 70m² or less (internal floor area)
    • At least 2 metres from any boundary or other residential building
    • Lightweight timber or steel framing

    If your project doesn't meet all conditions, we'll advise you on the standard building consent pathway instead.

    Step 3
    Both

    Site due diligence & checks

    Before any design work, we need to understand your site properly. You'll need to check a few things with your council, and we'll assist throughout.

    • Check the NES-DMRU (National Environmental Standards) — this determines if you also need a resource consent under the RMA
    • Review your council's district plan for any site-specific rules
    • Identify any natural hazards (flooding, slippage, erosion, subsidence)
    • Check if development contributions will be payable (amounts vary by council)
    • Speak to your bank and insurer early — they'll want to know what documentation to expect

    If natural hazards are present on your land, we must show adequate mitigation in the design. If this isn't possible, a standard building consent will be required.

    Phase 2 — Design & PIM Application

    Step 4
    Both

    Sign your design contract with us

    ArchSolutioNZ acts as your Licensed Building Practitioner (LBP) designer. We'll provide a written contract outlining the scope of design work, fees, and responsibilities.

    • We strongly recommend having your lawyer review the contract before signing
    • The contract covers preliminary plans, the PIM application, full construction plans, and the Certificate of Work
    Step 5
    ArchSolutioNZ

    Preliminary design plans prepared

    We prepare preliminary design plans to accompany your PIM application. These include site plans, elevations, and basic sections.

    • Plans show the building is standalone, new, ≤70m², and single storey
    • Natural hazard mitigation is incorporated where required
    • You review and approve the preliminary design before the PIM is lodged
    Step 6
    You

    Apply for your PIM

    The PIM is a mandatory step — you must receive it before any building work begins. We'll help you prepare the application (Form 2AA) and submit it through your council's portal.

    • Submit: completed Form 2AA, preliminary design plans, and description of the proposed work
    • Pay the council's PIM application fee (amount varies by council)
    • The PIM is not an approval — it's an information document from the council about your site

    You cannot legally start any building work until your PIM has been issued.

    Step 7
    Council

    Council processes and issues the PIM

    The council reviews your application and issues the PIM along with additional information about your site. It will include:

    • Whether your proposal appears to meet the exemption criteria
    • Any natural hazards identified on your land
    • Relevant heritage status, bylaws, infrastructure availability, and district plan requirements
    • A development contribution notice if applicable (stating the amount you'll need to pay on completion)
    • Confirmation that you have two years from this date to complete the build

    The council's clock on 10 working days pauses if they need more information from you. Make sure your application is complete to avoid delays.

    Step 8
    ArchSolutioNZ

    Review PIM & finalise full design

    We carefully review all council-provided information and update the design as needed. We then develop the complete construction plans and specifications.

    • Full architectural plans including structure, cladding, plumbing and drainage layout
    • All plans checked against every relevant Building Code clause
    • We issue a Certificate of Work (CoW) — our formal declaration that the design complies with the Building Code
    • Final plans and CoW are provided to you

    Phase 3 — Pre-construction preparation

    Step 9
    You

    Arrange finance & insurance

    Because there's no code compliance certificate issued under the exemption, lenders and insurers need other assurances. Set this up early so there are no surprises.

    • Provide your lender with the PIM, preliminary design plans, and information about your licensed professionals
    • Confirm with your insurer what documentation they'll require at completion
    • Arrange construction insurance to cover the build period
    • Ask about stage payment release requirements — your lender may want QA reports at key stages
    Step 10
    You

    Select your LBP builder

    All restricted building work on your granny flat must be carried out or supervised by a Licensed Building Practitioner (LBP). You can verify any builder's licence at lbp.govt.nz.

    • Get at least two or three quotes
    • Check the builder's LBP licence class covers the work (structure, external moisture management)
    • Confirm they have appropriate insurance in place
    • Ask what warranties they offer beyond the 12-month statutory defect repair period
    • The builder must provide a disclosure statement and standard checklist before you sign anything

    ArchSolutioNZ can recommend experienced LBP builders we've worked with if you need help finding the right person.

    Step 11
    Both

    Sign a written building contract

    For any residential building work costing $30,000 or more, a written contract is mandatory under the Building Act. This protects both you and your builder.

    • The contract must cover: scope of work, timeline, payment schedule, and dispute resolution
    • Have your lawyer review the contract before signing
    • The contract must also specify who is responsible for obtaining approvals and collecting documentation
    • Implied warranties apply for 10 years regardless of contract terms

    Do not let building work start before the PIM has been issued and the contract is signed.

    Phase 4 — Construction

    Step 12
    Builder

    Building work begins on site

    The builder, tradespeople, and site manager work to the plans and specifications. Unlike normal consented work, there are no mandatory council inspections — so your own quality assurance is critical.

    • All work must comply with the New Zealand Building Code
    • The builder must supervise any unlicensed workers (eg apprentices)
    • Plumbing, drainage, gas, and electrical work must be carried out by appropriately licensed tradespeople
    • Your two-year PIM clock is running from the date the PIM was issued
    Step 13
    You

    Quality assurance checks at key stages

    Because the council does not inspect exempt work, you are responsible for ensuring quality checks happen. We strongly recommend professional QA inspections at each of the following stages:

    • Foundations — before concrete is poured; confirm location and structural soundness
    • Framing — before roof cladding goes on; check structure, bracing, and load capacity
    • Building wrap — before joinery is installed; critical for weathertightness
    • Pre-clad — check flashings and cavity systems for moisture management
    • Pre-line — insulation and services installed, building weathertight, before linings go up
    • Drainage — before trenches are filled in
    • Final — all work complete, ready for occupation

    Keep photographic records and site notes at every stage. Your lender may need these for stage payment releases, and insurers may ask for them at completion.

    Step 14
    ArchSolutioNZ

    Manage any variations to the design

    On-site changes happen. But any variation must be checked to confirm it doesn't breach the exemption conditions or the Building Code. Do not proceed with a change without first consulting us.

    • We assess the variation for compliance with the exemption conditions
    • If compliant, we update the drawings and revise the Certificate of Work
    • If a variation takes the build outside exemption conditions (eg floor area exceeds 70m²), all work must stop and a building consent must be obtained before continuing
    • Product substitutions (eg different cladding or roof material) must also be checked — they can affect the weight limits set in the exemption

    Never exceed 70m² internal floor area, change to heavier construction materials, or remove self-contained facilities — these will invalidate the exemption.

    Phase 5 — Completion & handover

    Step 15
    Both

    Collect all required documentation

    Under the Building Act, your granny flat is considered legally complete only once you have received all of the following from your licensed professionals:

    • Final design plans (updated to reflect what was actually built, including any variations)
    • Certificate of Work (CoW) from ArchSolutioNZ covering all restricted design work
    • Record of Work (RoW) from each LBP builder for restricted building work they carried out or supervised
    • Record of Work from your registered plumber/drainlayer for sanitary plumbing and drainage
    • Electrical certificate of compliance and electrical safety certificate
    • Gas certificate of compliance and gas safety certificate (if gas was installed)

    Chase these documents from your tradespeople as work is completed — don't wait until the very end. Your 20-working-day submission clock starts once you have received them all.

    Step 16
    You

    Submit all documentation to the council

    Once you have received all required documents (Step 15), you have 20 working days to submit them to the same council that issued your PIM. The council stores these on your property file — they do not assess them for compliance.

    • Submit: final design plans, Certificate(s) of Work, Records of Work (from LBPs and plumber/drainlayer), electrical and gas certificates
    • Note: LBPs are required to submit their Records of Work directly to the council as well — but you should confirm this happened

    Failing to submit within 20 working days is an offence — you can be issued an infringement notice ($500) or fined up to $1,000.

    These records will appear on any future Land Information Memorandum (LIM) for your property, supporting resale, insurance, and lending.

    Step 17
    You

    Pay development contributions

    If the council issued a development contribution notice alongside your PIM, you must pay it within 20 working days of completing the build. The amount was fixed at the PIM stage.

    • Amounts vary by council, size of the granny flat, and whether NUO connections are required
    • Payment can be made to the council directly — check the contribution notice for details
    • If the design changed significantly during the build, discuss with the council whether the amount needs reassessing
    Step 18
    You

    Notify your bank & insurer

    Your bank may need to release final drawdown funds, and your insurer needs to switch from construction cover to permanent dwelling cover.

    • Provide: final plans, Records of Work, Certificates of Work, energy safety certificates, and proof of council submission
    • Confirm natural hazards commission (EQC) cover eligibility with your insurer
    • No code compliance certificate is issued under the exemption — your documentation package replaces this for insurance and lending purposes

    Phase 6 — Done

    Step 19
    You

    Move in & retain your records

    Congratulations — your granny flat is now a lawful building under the Building Act. Keep all documentation stored safely, as you'll need it for:

    • Future alterations (any changes to the granny flat follow the rules for existing buildings — some work may need a building consent)
    • Selling your property — your granny flat records will appear on the LIM
    • Insurance claims — insurers may ask to see your Records of Work and plans
    • Defect claims — your builder is liable to fix defects for 12 months; implied warranties run for 10 years

    Installing a solid fuel heater, adding a deck, or making structural alterations later will each require checking the relevant consent pathway — contact ArchSolutioNZ before starting any future work.

    Key deadlines to keep in mind

    Council issues PIM within 10 working days of a complete application · Build must be complete within 2 years of PIM issue date · Submit all documentation within 20 working days of completion · Pay development contributions within 20 working days of completion